Calendar

Parent page: Orchestrator › Process Audience: Developers Prerequisites: Developer role


Overview

The Process › Calendar screen shows on a calendar when processes are planned to run. The screen is for viewing only; records are not added or changed from the calendar, and entries cannot be dragged.

Only processes assigned to at least one resource appear on the calendar:

  • Automate processes are shown in purple. Each time range in the process's run times (from the Work Dates template or from the process form) is drawn as an entry on the matching weekdays, within the process's start and end dates. A 00:00–24:00 range appears as an all-day entry.

  • Schedule processes are shown in blue. Each enabled schedule is expanded within its own start and end dates: Daily, Weekly, Monthly, Yearly and Once schedules give a single entry at the start time; Hourly and Minutely schedules give an entry each day that covers the start–end time window.

  • On-Demand processes do not appear on the calendar.

Holidays are not taken into account for Automate process entries; entries also appear on holidays. Processes that have a holiday do not run on it; see the Holidays page for details. The meaning of the colours is not explained on the screen.


Month View

Process › Calendar — Month View

Process › Calendar — Month View

Filters

They are lined up above the calendar, without labels. The calendar is redrawn whenever one of them changes.

Filter

Description

Default

Branch

Filters processes by their branch.

All Branches

Resource

Shows only processes assigned to the selected resource.

All Resources

Process

Shows only the selected process.

All Processes

Scheduled Processes Visible / Hidden

Turns the entries of Schedule processes on or off.

On

Automated Processes Visible / Hidden

Turns the entries of Automate processes on or off.

On

If both switches are turned off, the calendar appears empty.

Navigation and views

Button

Description

‹ / ›

Moves to the previous or next month, week or day.

Today

Returns to the period that contains today.

Month / Week / Day / List

Changes the view. Month is the default view; the week starts on Monday.

In the month view, a "+N more" link appears for entries that do not fit in a day. Clicking a day or week number opens that day or week.


Entry Details

Hovering over an entry opens its details; in the Week, Day and List views the same information is written under the entry.

Process › Calendar — List View

Process › Calendar — List View

Line

Description

Frequency

For Automate processes, the time range, e.g. "Frequency between 12:00 and 24:00". For Schedule processes, the schedule type and frequency, e.g. "Daily Type - with 1 frequency", "Hourly Type - with 3 frequency between 20:00 and 23:45", "Weekly Type - will be running on …". The schedule type is written with its English name in both languages.

Branch

The process's branch.

Resources

The resources the process is assigned to, each as "Description (Name)".

Clicking an entry opens that process's details on the Processes screen if the process belongs to the active branch. Entries of processes in other branches cannot be clicked.