Flowchart

Runs activities as nodes linked to each other by connections on a canvas. The flow starts from the Start icon and follows the connections; Flow Decision is used to branch on a condition, Flow Switch to branch on a value.


⬇️MISC

Parameter

Type

Default

Description

ValidateUnconnectedNodes

Boolean

False

If True, the workflow reports a validation error when there is a node that cannot be reached from Start (unconnected); the settings of unconnected nodes are also validated. If False, unconnected nodes are ignored and do not run.


Usage

  • Activities, Flow Decision and Flow Switch are dragged and dropped onto the flowchart canvas. Nodes are connected by dragging from a node's connection point to the other node.

  • A connection is drawn from the Start icon on the canvas to the first node; the flow starts from this node. If there are nodes on the canvas but Start is not connected, the workflow reports a validation error. If there are no nodes, the flowchart ends without doing anything.

  • Only one outgoing connection can be drawn from an activity node; when the activity finishes, the node at the target of this connection runs. Flow Decision has separate exits for True and False, and Flow Switch for each case and Default.

  • A node can have multiple incoming connections. A loop can be built by drawing a connection to an earlier node.

  • When a node with no outgoing connection finishes (or if the selected branch is not connected), the flowchart completes.