# 💻 Resources

**Parent page:** Orchestrator › Reports **Audience:** Operations and monitoring teams, capacity planners **Prerequisites:** Monitor role


---

## Overview

The **Reports › Resources** screen (page title **Resource Report**) shows how much time robot resources spent running each process in the selected period. Each row is a process; the time is the total time the resources spent in the **Running** state for that process. Clicking a process name opens the breakdown of the time by day.

How it differs from screens with the same name or similar information:

* [Resource › Resources](/doc/resources-wsfqmLLOto): the screen where resource definitions and resource actions (start, stop, restart) are managed; it shows no durations.
* [Dashboards › Resource](/doc/resource-cZkiAC2MlA): its rows are resources; it gives each resource's work and idle time, their percentages and a chart. This report totals by process instead.
* [Dashboards › Resource Live](/doc/resource-live-k2dlTfc2ty): the current state of the resources; it has no past period.

On this page you will learn:

* Who can open the report and how the time is calculated
* The date options and the range each one covers
* Filters: resource, branch, process and working state
* A process's daily breakdown
* Exporting to Excel

 ![Resource Report — Last 7 Days](https://outline-production-attachments.s3-accelerate.amazonaws.com/uploads/a406920a-3878-4f5f-8f8b-7593ba62e617/cc72717a-fb65-4f1c-a3c4-18932830bc9f/report-resources.png?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=AKIA4EOUDTOVUICLPZ4P%2F20261123%2Fus-east-1%2Fs3%2Faws4_request&X-Amz-Date=20261123T231500Z&X-Amz-Expires=86400&X-Amz-Signature=d3fcea7a242d8aeb6899f77f1f062dadcf137658fb2690b995343fbb0ad98d00&X-Amz-SignedHeaders=host&x-amz-checksum-mode=ENABLED&x-id=GetObject " =2800x1986")


---

## Who can open it and what is listed

Only users with the **Monitor** role can open the screen. There is no hierarchy between roles; the **Admin**, **Developer** or **End User** role alone is not enough (see [User › Users](/doc/users-z8TpALpmBU)). A user without the role does not see **Resources** under Reports in the menu; opening the address directly redirects to the Home page.

| Topic | Rule |
|-------|------|
| Processes | Processes in all branches the user is authorized for; the list is not limited to the branch selected in the top bar. Disabled processes are listed too. |
| Total Work Time | The sum of the time the resources spent in the **Running** state while running this process in the period. All resources are added up: if two resources ran the same process at the same time for one hour, two hours are shown. |
| Period boundary | For runs that started before the period or are still going at its end, only the part inside the period is counted. |
| Processes that did not run | When the working state filter is empty, processes that did not run at all in the period are also listed, with *00.00:00:00*. |

This report has no work counts; for work counts per process use [Reports › Processes](/doc/processes-5CANpBTA7d).


---

## Date selection

The calendar button at the top right shows the selected range. When the screen is opened from the menu, **Today** is selected. Selecting an option reloads the page. The menu and the **Date Range** window are the same as in the [Works](/doc/works-Ij43iueeYk) report.

| Option | Range covered |
|--------|---------------|
| Today  | From 00:00 today to now |
| Yesterday | All of yesterday |
| Last 7 Days | From the start of the day 7 days ago to now (today included) |
| Last 30 Days | From the start of the day 30 days ago to now (today included) |
| This Month | From the 1st of the month to now |
| Last Month | All of last month |
| Date Range | Between the start and end times selected in the window; the start is included, the end time is not |

Times are in the company's time zone.


---

## Filters

The **Filters** button with the magnifier icon, to the left of the calendar button, opens the **Resource Report Filters** window. All fields are optional and empty (**Select**) by default. Changes are applied only with **Search**; closing the window with **Close** discards them. The window has no clear button.

 ![Resource Report Filters Window](https://outline-production-attachments.s3-accelerate.amazonaws.com/uploads/a406920a-3878-4f5f-8f8b-7593ba62e617/26642ba7-1ab8-47e9-86d0-33eb8aed7e16/report-resources-filters.png?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=AKIA4EOUDTOVUICLPZ4P%2F20261123%2Fus-east-1%2Fs3%2Faws4_request&X-Amz-Date=20261123T231500Z&X-Amz-Expires=86400&X-Amz-Signature=cb5ac26bd2369fc567de2eac3cc23f173de2a12a24aa273c5fcde9341f154683&X-Amz-SignedHeaders=host&x-amz-checksum-mode=ENABLED&x-id=GetObject " =2552x662")

| Field | Description |
|-------|-------------|
| Resource | When selected, only the work time on that resource is counted. |
| Branch | When selected, only the processes of that branch are listed. |
| Process | When selected, only that process is listed. The list is grouped by branch. |
| Process Working State | **Working**: only processes that ran in the period. **Not Working**: processes that did not run at all in the period. When empty, both are listed. |

* **Branch** and **Process** cannot be used together: selecting one disables the other.
* Selecting a branch or process the user is not authorized for returns an empty report.


---

## Records table

If there are no processes to list in the selected period, **No data found.** is shown instead of the table.

| Column | Description |
|--------|-------------|
| \#     | Row number  |
| Process | Process name; clicking it opens the process's details window (see below). |
| Master Project | The process's master project |
| Branch | The process's branch |
| Total Work Time | The total time the resources ran the process, in *days.hours:minutes:seconds* (e.g. *00.06:53:27* = 6 hours 53 minutes 27 seconds) |

* The last row of the table is **Total**: the total work time of all processes.
* Processes that ran in the period come first, followed by those that did not. Clicking a column header sorts the table on the page by that column. There is no search or paging.

### A process's daily breakdown

Clicking a process name opens the **<process name> Details** window on the same page.

 ![Process Details Window — Daily Work Times](https://outline-production-attachments.s3-accelerate.amazonaws.com/uploads/a406920a-3878-4f5f-8f8b-7593ba62e617/8b836151-b30a-4b07-8b26-a3946a0e23d5/report-resources-details.png?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=AKIA4EOUDTOVUICLPZ4P%2F20261123%2Fus-east-1%2Fs3%2Faws4_request&X-Amz-Date=20261123T231500Z&X-Amz-Expires=86400&X-Amz-Signature=fc544bf13aaa693fb3fc38fa2d00fb4150e7c1e5a71ea4c1172e34bbea5e11f2&X-Amz-SignedHeaders=host&x-amz-checksum-mode=ENABLED&x-id=GetObject " =2552x1160")

* At the top, the process's **Master Project** and **Branch** are shown read-only.
* The table has one row for each day of the period: **#**, **Work Date**, **Total Work Time**. Rows are sorted newest first; days on which the process did not run are included with *00.00:00:00*. The days add up to the time in the main table.
* The **Download** button downloads this process's daily list as an Excel file (see below); it is disabled when there is no daily data.
* **Close** closes the window.


---

## Exporting to Excel

| Button | File | Content |
|--------|------|---------|
| Download Report (Excel icon, at the top) | `ResourceReport_<ddmmyyyy>.xlsx` | Two sheets. **Total**: Process Name, Master Project, Branch, Total Work Time and the total at the bottom. **Daily**: the day rows of all processes (Process Name, Master Project, Branch, Work Date, Total Work Time), newest first, with the total at the bottom. |
| Download (in the details window) | `ResourceReport_<ddmmyyyy>.xlsx` | A single sheet **Sheet1**: only that process's day rows (Process, Master Project, Branch, Work Date, Total Work Time) and the total. |

* The selected date option and filters are applied; the data is read again at download time.
* Both files have the same name; if you download both on the same day, the browser may rename the second one.

There is no PDF or chart download.


---

## Notes

* The report does not refresh by itself; the times are the values at the moment the page was loaded. With options such as **Today** and **Last 7 Days**, runs still in progress are counted up to that moment.
* There are no buttons that start, stop or restart a resource; these actions are on the [Resource › Resources](/doc/resources-wsfqmLLOto) screen.